Single-storey extensions and permitted development
Permitted development can provide a route to a single-storey extension without a full planning application, but only when every relevant condition is met. The familiar rear-depth limits are one part of the rules, not the whole test. Larger rear extensions have a separate prior approval process, and building regulations still apply. This guide explains the general England framework. Confirm the current rules, property history and any restrictions with your council before relying on them for your address.
Want a professional to handle it?
Quantum Eco manages building, plumbing, electrics, carpentry and tiling in-house. Quotes are free.
Frequently asked questions
Start with the ordinary rear extension limits
For a single-storey rear extension under the ordinary householder permitted development rules, the usual maximum projection beyond the rear wall of the original house is 3 metres for an attached house and 4 metres for a detached house. The maximum overall height is 4 metres. If the extension is within 2 metres of a boundary, its eaves must not exceed 3 metres.
The original house means the house as first built, or as it stood on 1 July 1948 if built earlier. Previous extensions count when assessing what remains possible. Removing an old addition does not turn a later wall into the original rear wall, and unusual rear elevations can require careful interpretation.
Other conditions also apply, including restrictions on coverage, position and materials. Measure from the correct walls and show the existing building clearly on drawings. Ask the council to assess awkward footprints rather than applying the headline depth to whichever wall gives the largest result.
Use prior approval for a larger rear extension
The larger home extension scheme can allow single-storey rear projections up to 6 metres for an attached house or 8 metres for a detached house, subject to the rules and the prior approval process. It is not an automatic extra allowance added to an existing extension. Height and the other applicable conditions still matter.
Before starting, submit the required information to the local planning authority for the neighbour consultation and prior approval procedure. Where objections are received, the authority considers the effect on adjoining premises' amenity through that process. Neighbour support alone is not a substitute for making the submission or obtaining the required outcome.
This route is not available on article 2(3) designated land, including conservation areas, or on Sites of Special Scientific Interest. Confirm eligibility and the procedural requirements with the council. Do not begin simply because an installer says an extension of that depth is common locally; follow the statutory process before construction.
Check side extensions, coverage and materials
A single-storey side extension must not exceed 4 metres in height or half the width of the original house. Extensions forward of the principal elevation, or a side elevation fronting a highway, are not permitted by the ordinary Class A extension rules. Side and rear combinations require care because both sets of relevant restrictions can apply.
Buildings and additions, excluding the original house, must not cover more than 50% of the total curtilage area excluding the original house's footprint. Existing outbuildings and previous additions can therefore constrain a proposal that otherwise meets the rear-depth limit. A properly measured site plan is more useful than an estimate based only on the visible lawn.
Exterior materials must be of similar appearance to those of the existing house, with the relevant exception for conservatories. Consider walling, roof finish and how new work meets the old. Permitted development is not a general permission to choose any contrasting external finish, even if the overall shape complies.
Identify properties where the normal route changes
Flats and maisonettes do not have householder extension permitted development rights. Listed buildings require separate heritage consideration, and listed building consent may be needed for alterations affecting their special interest. Planning conditions, Article 4 directions and certain previous changes of use can also restrict the available rights.
On article 2(3) designated land, including conservation areas, side extensions are not permitted development under Class A, and additional restrictions apply to exterior cladding. Ordinary single-storey rear extensions may still be possible within the applicable conditions, but the larger home extension prior approval route is not available there.
Check the council's mapping, the property's decision notices and any restrictions for the address. A neighbour's recent extension might have full planning permission or a different planning history. If the proposal falls outside permitted development, a householder planning application may still be a realistic route, assessed on its own merits.
Keep building regulations and structural design separate
An extension that is permitted development still generally requires building regulations approval. Structure, foundations, fire safety, insulation, ventilation, drainage and safe electrical work need coordinated design. Planning lawfulness does not tell you what size beam is required or whether the existing drain arrangement can serve the new layout.
Opening the rear of the house can have structural consequences well beyond the new walls. Establish the support strategy, temporary works and inspection requirements before removing loadbearing construction. A larger kitchen also needs thought about extraction, glazing, overheating and the relationship between cooking space and escape routes.
Existing sewers, boundary construction and work near neighbouring structures may introduce separate permissions or Party Wall etc. Act procedures. These are not resolved by a permitted development certificate. Ask the relevant professionals to identify them early so the design and work sequence are based on more than the planning envelope alone.
Put the evidence in place before starting
For a proposal within ordinary permitted development, a certificate of lawfulness of proposed development can provide formal evidence of the position. Supply accurate existing and proposed drawings, dimensions and property-history information. A certificate is not a relaxation of the rules and only supports the development actually described.
For larger rear extensions, use the correct prior approval route before work begins. For proposals outside the conditions, obtain planning permission instead. Keep the planning outcome, any certificate, building control documents and construction drawings together so changes can be checked against the right approval rather than an old sketch.
Quantum Eco can discuss the practical implications of foundations, structural openings, kitchen layouts and access during a site visit. Confirm the planning route with your council first, then develop a coordinated scope. Agree the specification and work arrangements in writing, with any unresolved consent or structural matters clearly identified before construction is authorised.
Plan a buildable extension, not just a permitted footprint
Call Charles on 07888 775897 for a free site visit and free quote for your single-storey extension, including the practical construction and layout questions.
Related services
Based in Broadstairs, covering Thanet, Canterbury and East Kent.
Related pages
More guides
Planning Permission & Regulations
Building in conservation areas across East KentStructural Work & Repairs
Removing a load-bearing wall safelyPlanning Permission & Regulations
Garden room planning permission in Thanet